Glossary: Asbestos Notification System FAQ
REVISIONS

How do I change other information on my J#?

You may login to the Online Asbestos Notification System and click the “Edit Job Details” button from your Asbestos Notification Summary Page to revise the following information:

i. Contractor Company Information – please see Question #61.

ii. Contractor or Individual Contact Information

iii. Job Start and Completion Dates

iv. Waste Disposal Site

v. And for Planned Renovations, you can upload a revised Work Schedule Document


How do I revise my Start and Completion Date for my J#?

a. You may login to the Online Asbestos Notification System and click the “Edit Job Details” button from your Asbestos Notification Summary Page to revise your Start and Completion Dates. 

b. The Start Date cannot be revised after your Start Date has past. You have until 11:59 pm on your Start Date to revise the Start Date.  After that time, the system will no longer allow you to revise your Start Date.  [JC1] 

c. The Completion Date cannot be revised after your Completion Date has past.  You have until 11:59 pm of your Completion Date to revise your Completion Date.  After that time, the system will no longer allow you to revise your Completion Date and the J# will expire.

I don’t see the “Change Job Details” button. Why?

After your project’s Completion Date has past, you will no longer see a “Change Job Details” button on your Asbestos Notification Summary Page.

SURVEY

Do I need a survey?

A survey is required for all demolitions.


How do I know if my surveyor/Certified Asbestos Consultant is state-certified?

The Division of Occupational Safety and Health maintains a list of State-Certified Asbestos Consultants and Site Surveillance Technicians.  Please visit their Search page for more information.

I don’t have a survey. Can I still submit my Demolition Notification?

A survey is not required to submit your Demolition Notification.  However, a survey report must be provided onsite.  Failure to do so may lead to a Notice of Violation.

If my building was built last year, do I still need a survey?

A survey is required regardless of the date of construction.

What is a CAC/SST #?

Certified Asbestos Consultants and Site Surveillance Technicians are issued a certification number by the State of California.

Where can I get a list of the certified asbestos analysis laboratories in the Bay Area?

A list of certified asbestos analysis laboratories can be found by conducting an online search.


WITHDRAWALS

I don’t see a withdrawal button anymore. How do I withdraw my job?

After your project’s Start Date has past, you will no longer see a “Withdraw” button on your Asbestos Notification Summary Page.  To report a withdrawal after the Start Date, please call the Asbestos Help Desk.

What is a withdrawal?

The system defines a withdrawal as a cancellation initiated by an external user.  When an Air District employee cancels a notification, it is called a cancellation.