Does my demolition qualify as a fire-training training demolition?

a.  Yes, if a local fire department is using your building for fire training.  Any structure used for fire training is reclassified as a Government Building. 

b. Additionally, fire training also requires a Regulation 5 notification (Open Burn).

c. A Renovation notification will be required if there is >100 square or linear feet of RACM.  ALL asbestos containing material must be removed before the fire training.   

d. Fire Training cannot be the final means of demolition.  A separate demolition Notification must be submitted by a demolition contractor for final demolition.